CompTIA E2C Project Certification Exam

Question No: 111 – (Topic 2)

Which of the following are common causes of project team conflict? (Select Two).

  1. Project schedule

  2. Competing resource demands

  3. Project budget

  4. Varying work styles

  5. Time zone differences

Answer: B,D

Question No: 112 – (Topic 2)

Which of the following would be included in a project scope document? (Select Three).

  1. Project constraints

  2. Gantt chart

  3. Work Breakdown Structure (WBS)

  4. Project roles and responsibilities

  5. Key Performance Indicators (KPIs)

  6. Detailed project objectives

Answer: A,E,F

Question No: 113 – (Topic 2)

A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?

  1. Construct a detailed plan to implement the change.

  2. Analyze the impact of the change request.

  3. Document the request in the change control log.

  4. Request a meeting with the project sponsor to discuss scope creep.

Answer: A

Question No: 114 – (Topic 2)

Which of the following activities occur during a project kick-off meeting? (Select Three).

  1. Review of the risk management plan

  2. Review of the roles and responsibilities

  3. Review of the work breakdown structure (WBS)

  4. Review of the change management procedures

  5. Review of the project goals and objectives

  6. Review of the stakeholder expectations

Answer: B,E,F

Question No: 115 – (Topic 2)

Which of the following personnel should sign the project charter?

  1. A representative from the project management office

  2. The project manager

  3. The most senior project team member

  4. An executive with the power to authorize the project

Answer: D

Question No: 116 – (Topic 2)

An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on the project?

  1. Cost will decrease and time will increase.

  2. Cost will decrease and time will decrease.

  3. Cost will increase and time will increase.

  4. Cost will increase and time will decrease.

Answer: D

Question No: 117 – (Topic 2)

Which of the following activity sequencing methods describes the start-to-start dependency?

  1. The completion of the successor activity depends upon the beginning of the predecessor activity.

  2. The completion of the successor activity depends upon the completion of the predecessor activity.

  3. The beginning of the successor activity depends upon the completion of the predecessor activity.

  4. The beginning of the successor activity depends upon the beginning of the predecessor activity.

Answer: D

Question No: 118 – (Topic 2)

A project manager is performing activity duration estimation for a project. Using expert judgment the project manager has three values for each activity: the worst case, most likely case, and best case. Which of the following tools would be the BEST to use?

  1. Gantt chart

  2. PERT

  3. EVM

  4. GERT

Answer: B

Question No: 119 – (Topic 2)

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

  1. Arrow Diagramming Method (ADM)

  2. Precedence Diagramming Method (PDM)

  3. Critical Path Method (CPM)

  4. Critical Chain Method (CCM)

Answer: B

Question No: 120 – (Topic 2)

A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?

  1. Critical Chain Method (CCM)

  2. Precedence Diagramming Method (PDM)

  3. Arrow Diagramming Method (ADM)

  4. Critical Path Method (CPM)

Answer: D

100% Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass JK0-017 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE