CompTIA E2C Project Certification Exam

Question No: 161 – (Topic 2)

A Pareto chart is a special type of:

  1. histogram.

  2. Ishikawa diagram.

  3. scatter diagram.

  4. run chart.

Answer: A

Question No: 162 – (Topic 2)

Which of the following is true of a work breakdown structure (WBS)? (Select Two).

  1. It consists of work packages at the top level which are decomposed to increasingly detailed levels.

  2. It is a quantitative analysis tool used in quality management to analyze defects.

  3. Each descending level represents an increasing detailed definition of the project work.

  4. It is developed during the planning process and used to create the project scope statement.

  5. It organizes and defines the total scope of the project.

Answer: C,E

Question No: 163 – (Topic 2)

Which of the following is a benefit of a work breakdown structure (WBS)?

  1. It can determine the amount of progress on the project.

  2. It can quickly identify the projects major deliverables and underlying activities with graphical representation.

  3. It can quickly identify the probability and impact of project risks.

  4. It allows a real time analysis of actual project costs compared to the project baseline to determine the project variances.

Answer: B

Question No: 164 – (Topic 2)

Which of the following describes a work breakdown structure (WBS) dictionary?

  1. A high level requirements document used to create the WBS.

  2. An alphabetical listing of WBS components detailing their associated project schedule dependencies.

  3. An organizational reference defining how WBS levels must be decomposed.

  4. A supporting document that provides more detail for the WBS components.

Answer: D

Question No: 165 – (Topic 2)

Which of the following would require that the project risk register be updated?

  1. A qualitative risk analysis is performed

  2. A stakeholder has concerns about material delays

  3. The risk management plan is created

  4. Increased costs for required materials

Answer: A

Question No: 166 – (Topic 2)

The change control board has just approved a request to modify the sampling technique for a project. Which of the following documents would the project manager update?

  1. Risk management plan

  2. Quality management plan

  3. Communication management plan

  4. Scope management plan

Answer: B

Question No: 167 – (Topic 2)

A project manager is comparing their budgeting techniques to the most successful project in the companys history. Which of the following techniques is being utilized?

  1. Benchmarking

  2. Return on investment

  3. Process analysis

  4. Cost-benefit analysis

Answer: A

Question No: 168 – (Topic 2)

A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?

  1. Risk response strategies

  2. Risk register

  3. Risk assessment

  4. Stakeholder risk tolerance

Answer: A

Question No: 169 – (Topic 2)

A project manager can create a risk breakdown structure (RBS) to determine which of the following?

  1. Risk tolerance

  2. Risk probability

  3. Risk category

  4. Risk impact

Answer: C

Question No: 170 – (Topic 2)

The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?

  1. Communication plan

  2. Risk plan

  3. Scope plan

  4. Quality plan

Answer: A

100% Free Download!
Download Free Demo:JK0-017 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass JK0-017 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE