CompTIA Project Certification

Question No: 41 – (Topic 1)

Which of the following represents a good reason for formally closing out a project?

  1. To provide historical information for future projects

  2. To manage stakeholders’ expectations

  3. To promote team cohesiveness

  4. To keep a record in case someone comes back later with an issue after transition

Answer: A

Question No: 42 – (Topic 1)

Which of the following are the characteristics of a project? (Select TWO).

  1. Contains a procurement plan

  2. Utilizes a chart of accounts

  3. Requires resource leveling

  4. Definitive beginning and end

  5. Produces a deliverable

Answer: D,E

Question No: 43 – (Topic 1)

An email to end users regarding the go-live of an upcoming software release is an example of:

  1. interactive method.

  2. push method.

  3. formal method.

  4. pull method.

Answer: B

Question No: 44 – (Topic 1)

A widget being built for a construction project has undergone quality review. After the review, a report is provided showing the frequency of defects with a threshold showing where the majority of the issues are coming from. Which of the following is the tool being used?

  1. Run chart

  2. Pareto diagram

  3. Gantt chart

  4. Scatter diagram

Answer: B

Question No: 45 – (Topic 1)

Which of the following has occurred when project costs are baselined?

  1. The project manager has determined when they will need to make purchases

  2. The project costs have been spent

  3. The business has approved the budget

  4. The estimated costs of the project are fixed

Answer: D

Question No: 46 – (Topic 1)

Which of the following plans would include provisions for extended project support and warranties?

  1. Procurement

  2. Transition

  3. Quality management

  4. Cost management

Answer: B

Question No: 47 – (Topic 1)

A third party product warranty is an example of which of the following types of risk response?

  1. Risk sharing

  2. Risk avoidance

  3. Risk acceptance

  4. Risk transfer

Answer: D

Question No: 48 – (Topic 1)

A software project has just been completed. While measuring the success of the project, the project manager has found that the customer is dissatisfied with the functionality. Which of the following components has suffered in this project?

  1. Risk

  2. Quality

  3. Schedule

  4. Budget

Answer: B

Question No: 49 – (Topic 1)

A project manager has been presented a set of documents containing why a project is needed, how it fits in with the company objectives, and the revenue that will be generated by the product. Which of the following has the project manager just received?

  1. A business case

  2. A charter

  3. Key project deliverables

  4. Project objectives

Answer: A

Question No: 50 – (Topic 1)

Which of the following can aid in the identification of the cause of the majority of the defects on a given project?

  1. Ishikawa diagrams

  2. Run charts

  3. Histograms

  4. Pareto charts

Answer: D

100% Free Download!
Download Free Demo:PK0-003 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass PK0-003 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE