Question No: 71 – (Topic 1)

A project manager was informed that a task will be delayed by four weeks. To determine the impact on the overall project, which of the following will the project manager need to update FIRST?

  1. WBS

  2. Risk log

  3. Project schedule

  4. Scope statement

Answer: C

Question No: 72 – (Topic 1)

While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?

  1. Stakeholder register

  2. Issue log

  3. Risk register

  4. Change log

Answer: B

Question No: 73 – (Topic 1)

Which of the following types of organizational structures groups personnel by both functions and projects?

  1. Project based

  2. Virtual

  3. Functional

  4. Matrix

Answer: D

Question No: 74 – (Topic 1)

A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is:

  1. re-direct the development team.

  2. create a change request.

  3. update the issues log.

  4. hold a meeting with the users.

Answer: B

Question No: 75 – (Topic 1)

The project team is geographically split between two time zones. Which of the following should be performed by the project manager?

  1. Escalate to the project sponsor with a preference to replace the remote members with

    local members.

  2. Set up meeting times that are not necessarily a perfect fit, but are fair to both locations.

  3. Schedule two separate meetings at the desired local time for the participants.

  4. Convert traditional meetings into email updates and catch up on an exceptions basis.

Answer: B

Question No: 76 – (Topic 1)

A quality control team is engaged in ensuring the quality of a production part. The team has just completed gathering performance information. Which of the following actions should be taken NEXT?

  1. Update quality control plan

  2. Generate change requests

  3. Identify variances

  4. Perform impact analysis

Answer: C

Question No: 77 – (Topic 1)

The scope document is created based on the direct input of which of the following documents?

  1. Cost management plan

  2. Organizational strategic goals

  3. Project charter

  4. Work breakdown structure

Answer: C

Question No: 78 – (Topic 1)

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST?

  1. Prepare performance report

  2. Manage the issue

  3. Schedule a meeting

  4. Update communication plan

Answer: B

Question No: 79 – (Topic 1)

A project manager schedules a weekly meeting to review the project schedule. The project manager is looking for an easy way to see the project tasks and review areas where tasks may overlap and are dependent on others. Which of the following would provide the project manager with the BEST project view?

  1. PERT

  2. Pareto

  3. CPM

  4. Gantt

Answer: D

Question No: 80 – (Topic 1)

The project team members have determined they need to procure hardware before they will be able to create a product to test. This activity sequencing was created using which of the following types of dependency?

  1. Mandatory

  2. External

  3. Discretionary

  4. Internal

Answer: A

100% Free Download!
Download Free Demo:PK0-003 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass PK0-003 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE