CompTIA Project Exam

Question No: 11

Two team members completely disagree on how to complete a specific task The project manager observes the conflict but takes no immediate action Which of the following techniques is the project manager using?

  1. Compromising

  2. Smoothing

  3. Withdrawing

  4. Accepting

Answer: C

Question No: 12

After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence and durations?

  1. Use milestones identified in the project charter.

  2. Use data based on past knowledge.

  3. Hold a full team workshop to review the complete WBS.

  4. Collaborate with other project managers.

Answer: A

Question No: 13

A company hires an outside vendor to provide 24/7 support Which of the following documents would determine the contractual obligations?

  1. PO

  2. SLA

  3. LOI

  4. MOU

Answer: B

Question No: 14

Which of the following describes risk mitigation?

  1. The transfer of the risk to another entity or project inside or outside the organization, along with associated costs

  2. The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence

  3. The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization

  4. The weighting or prioritization of the risk against all other identified risks within this project or others associated with it

    Answer: A

    Question No: 15

    The executive sponsor asks a project manager to summarize the following for a project:

    1. Final capital expenditures

    2. Anticipated cost of new employee resources to support the solution

    3. Maintenance estimates

      Which of the following information should the project manager provide?

      1. Cost baseline

      2. Burn rate

      3. Cost variance report

      4. Total project cost

Answer: D

Question No: 16

A customer has requested additional features for an active project. Which of the following steps should take place NEXT?

  1. Implement the requested changes.

  2. Evaluate the impact of the changes.

  3. Update all project documents.

  4. Submit the requested changes to the CCB

Answer: C

Question No: 17

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

  1. EAC

  2. BAC

  3. TCPI

  4. ETC

Answer: B

Question No: 18

A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take?

  1. Tell the senior manager the estimation is not available yet

  2. Use the budget from a similar project to generate estimates.

  3. Ask a SME for an opinion and propose an estimate.

  4. Gather the team to immediately generate estimates.

Answer: C

Question No: 19

The project manager has noticed a vendor is not performing in accordance with the SLA Which of the following items should the project manager use to highlight the vendor#39;s areas of poor performance?

  1. Balanced score card

  2. WBS

  3. Post-project evaluation

  4. PERT

Answer: B

Question No: 20

A milestone task on the critical path has been completed. Which of the following should the project manger notify?

  1. Owner of predecessor task

  2. Project team

  3. Project sponsor

  4. Project steering committee

Answer: B

100% Free Download!
Download Free Demo:PK0-004 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass PK0-004 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE