CompTIA Project Exam

Question No: 41

Which of the following is the primary purpose of an MOA or an MOU?

  1. State expectations of all signatory parties to reduce potential misunderstandings.

  2. Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.

  3. Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program

  4. Provide transparency to competitors regarding all signatory parties

Answer: D

Question No: 42

The key stakeholders have reported the project pace as being slow The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date To alter the pace of the project, which of the following should the project manager do FIRST?

  1. Give approval for the change requested by the project sponsor

  2. Deny the request from the project sponsor

  3. Document the change request from the project sponsor

  4. Ask the project sponsor to change the request.

Answer: A

Question No: 43

Which of the following metrics demonstrates to a project manager if a project is overspending or under spending ?

  1. EAC

  2. BAC

  3. CPI

  4. ETC

Answer: D

Question No: 44

A new stake holder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule project manager is concerned that the requests will lead to;

  1. quality control issues

  2. additional risks

  3. scope creep

  4. time constraints.

Answer: C

Question No: 45

A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager#39;s NEXT steps? (Select TWO)

  1. The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.

  2. The project manager should notify the project sponsor to update the schedule in the

    documentation because the project could potentially encounter delays.

  3. The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.

  4. The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.

  5. The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline

Answer: B,E

Question No: 46

Which of the following defines a group of projects that work together to achieve a common goal?

  1. Product

  2. Portfolio

  3. Program

  4. Project plan

Answer: B

Question No: 47

Several team members report that meeting objectives are not being met. Which of the following documents would a project manager create to make team meetings more effective? (Select TWO).

  1. Create an SOW prior to each meeting and adhere to it.

  2. Create a meeting agenda prior to each meeting and adhere to it.

  3. Create a lessons learned list prior to each meeting and adhere to it

  4. Create a project charter prior to each meeting and adhere to it.

  5. Create an action item list during the meeting and adhere to it.

  6. Create a corrective action plan prior to each meeting and adhere to it.

  7. Create a WBS prior to each meeting and adhere to it.

Answer: C,D

Question No: 48

V project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

  1. Project schedule

  2. Cost plan

  3. Scope statement

  4. Impact assessment

Answer: C

Question No: 49

A business has implemented a new online performance management tool that allows functional and project managers to rate employees online This action is known as which of the following?

  1. Business process change

  2. Organizational change

  3. Internal reorganization

  4. Business continuity planning

Answer: A

Question No: 50

The project sponsor has cut the resources required for project completion The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?

  1. The project manager should identify and document the reasons for the additional resources in a change request

  2. The project manager should hire additional resources temporarily to complete the project

  3. The project manager should terminate the project until additional resources are added to the project.

  4. The project manager should ask the project team members to take on more tasks to complete the project on time

Answer: A

100% Free Download!
Download Free Demo:PK0-004 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass PK0-004 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE